Creating the artificial beach in Sipopo
Description:
Creating a 1500-metre-long artificial beach in hydraulic backfill
Quantity of hydraulic backfill put in place: 331,730 m³
Year started: 2010
Duration of works: 12 months
Idatco share: 24.49 %
AéropBata Airport:
Description:
Phase 1: extension of the platform for the runway layout (aircraft used as reference: A380)
Creating a 38-hectare platform to bring Bata airport up to standard and for the type approval of the runway for the A380
Quantity of hydraulic backfill put in place: 2,016,266 m³
Year started: 2011
Duration of works: 10 months
Idatco share: 45.75 %
Phase 2: Adding 10 hectares to the platform for airport infrastructure facilities
Creating a 10 hectare platform for the airport infrastructure platform at Bata
Quantity of hydraulic backfill put in place: 255,496 m³
Year started: 2014
Duration of works: 2 months
Idatco share: 45.75 %
Port of Malabo
Description:
Construction of the port of Malabo
Backfilling of the bay from the port of Malabo
Quantity of hydraulic backfill put in place: 5,480,181 m³
Creating breakwaters in the port of Malabo
Quantity dredged: 400,000 m³
Year started: 2006
Idatco share: 15.61 %
Port of Bata
Description:
Construction of the extension of the port of Bata
Creating breakwaters in the port of Bata
Quantity dredged: 1,853,530 m³
Quantity of hydraulic backfill put in place: 2,728,104 m³
Year started: 2012
Duration: 42 months
Idatco share: 14.36%
Dredging of the channel at Corisco, Kogo, Aconeque and Port of Kogo and Aconeque
Customer: Somagec SUD and Somagec GE
Description:
Construction of the ports of Kogo and Aconeque
Dredging the access channel between Corisco, Kogo and Aconeque to meet a water depth of -7 metres
Dredging the mud at the port of Kogo
Quantity dredged: 2,835,046 m³
Year started: 2013
Duration: 18 months
Idatco share: 27.33 %
Creating an artificial island at Corisco
Description:
Creating an artificial island at Corisco
Quantity of hydraulic backfill: 1,601,755 m³
Year started: 2013
Duration: 50 months
Idatco share: 22.54 %
Floating dock phase II & III
Description:
Construction of a ship repair yard
Backfilling of the floating dock platform phase II & III
Quantity of hydraulic backfill: 646,400 m³
Year started: 2014
Duration: 36 months
Idatco share: 12.47 %
Protection of Utonde beach
Description:
Construction of a protected breakwater on the Utonde beach tourist coast
Backfill for the protection of Utonde beach
Quantity of hydraulic backfill: 509,718 m³
Year started: 2015
Duration: 15 months
Idatco share: 26.66 %